top of page

PROJECT 1

Newtown Creek, New York

Newtown Creek, New York presented MTS with a very unique challenge. XXX Company needed to relocate a 60' tall, 350,000 pound tank 100 yards within their facility. The problem was that there were obstacles, and the path to the new foundation was narrow and required a couple tight turns.

MTS utilized its Tank Turtles technology to safely and quickly move the tank into place. MTS lifted with 12 jacks and moved it with 10 Tank Turtles. The whole process to 8 days, much to the surprise and delight of the client. 

bottom of page